Projects Out to Bid

Title Bid Opening Bid Results
FOOTHILL BOULEVARD RESTRIPING PROJECT
FROM ALTA CANYADA ROAD TO OAK GROVE DRIVECONTRACT 19/20-6Request Full Bid PacketPlan Holder’s List
2:00 p.m. on Thursday, June 4, 2020 Bid Results

Requests for Proposals

Title Due Date
None

Capital Improvement Projects

Capital Improvement Projects (CIPs) are considered a major, non-routine expenditure for new construction, major equipment purchases or improvements to an existing building, facility, land, streets, storm drains, or utilities, or the expansion of the City parks system.

Active Project Status

UNDER CONSTRUCTION

Title Description Status
Lanterman House Maintenance The project includes: painting woodwork trim, reapplication of anti-slip tape, and repairs to the wood trellis. Contract was awarded on December 3, 2019; Start of construction is delayed to May 2020 due to the current “COVID 19 – “Staying Home Order”.

ESTIMATED COMPLETION DATE OF AUGUST 2020

2020 Citywide Street Resurfacing The project includes resurfacing of 23 street segments throughout the City, with an approximate distance of 4.5 miles. Bids were opened on March 12, 2020. City Council awarded a Contract, on April 7, 2020, to the lowest bidder Hardy & Harper, Inc. Construction is to start in June 2020

ESTIMATED COMPLETION DATE OF AUGUST 2020

Miscellaneous Concrete Repair The City maintains and repairs miles of curbs, gutters, and access ramps, as they are damaged by traffic or by tree roots or have simply deteriorated due to age or use. On May 5, 2020, the City Council awarded the Contract to the lowest bidder CT&T Concrete Paving, Inc., in the amount of $109,200. Construction is scheduled to start by June 30, 2020.

ESTIMATED COMPLETION DATE OF SUMMER 2020

IN DESIGN PHASE

Title Description Status
Seco Creek Trail The project involves environment analysis of the user made trail and construction to ensure the trail complies with current trail standards. Design= Completed Environmental Permits= In Progress

ESTIMATED START CONSTRUCTION DATE SUMMER 2020

Foothill Bouelvard Street Restripping The project includes restriping Foothill Boulevard from Alta Canyada Road east to Oak Grove Drive and striping median noses from Briggs Avenue to Oak Grove. Design= Completed
Project was advertised for construction bids on May 7, 2020 and bids to be opened on June 4, 2020.ESTIMATED START CONSTRUCTION DATE SUMMER 2020
Foothill Boulevard Link The project includes a half- mile long Class I bike trail between Hillard Avenue and Leata Lane; a 1.5 mile long Class II bike path; new landscaped medians and widened parkways, creating a pedestrian greenbelt. Design= In Progress Environmental= Complete ROW= Complete
Reuest for Approval to Advertise was submitted to Caltrans on May 14,2020.ESTIMATED START CONSTRUCTION DATE FALL 2020
Soundwall Phase II The project includes 1 wall segment to reduce exposure to traffic noise on the south side of the 210 Freeway from La Toure Way to Alta Canyada Road. Design= In Progress Environmental= Complete ROW= In Progress

ESTIMATED START CONSTRUCTION DATE FALL 2020

Green Alley Improvments The project includes the installation of a pervious pavement over an infiltration gravel bed in the alley north of Foothill Boulevard, between Indiana Avenue and Alta Canyada Road. Design= In Progress

ESTIMATED START CONSTRUCTION DATE SUMMER 2020

Soundwall Phase III The project includes 3 wall segments to reduce exposure to traffic noise on the north and south side of the Foothill Boulevard highway overpass. Design = In Progress
Environmental = In Progress
ROW = In progressESTIMATED START CONSTRUCTION DATE SUMMER 2020
Foothill Boulevard Traffic Signal Improvements The project includes safety improvements to existing traffic signals at 4 intersections with Foothill Boulevard to enhance safety at each intersection, reduce the potential for traffic collisions, and improve traffic flow. City Council awarded the Contract, on April 21, 2020, to Kimley-Horn & Associates, Inc. Currently, staff finalizing the agreement with the Consultant.

ESTIMATED START CONSTRUCTION DATE FEBRUARY 2021

Flint Canyon Trail Phase One of the project includes preliminary engineering (survey, topographic base mapping, geotechnical investigation, design alternative analysis); public outreach; and final plans, specifications, and estimate (PS&E) for construction. Design = In Progress
Environmental = In ProgressESTIMATED START CONSTRUCTION DATE DECEMBER 2020

FUTURE PROJECTS

Title Description Status
Descanso Drive Street Improvement Descanso Drive, from Chevy Chase Drive to Verdugo Boulevard, will be repaired with localized reconstruction and 2” AC overlay. City Council approved funding for half of the project, pending LA County commitment for remaining half of expense.
Foothill Blvd Debris Basin The project includes design and construction of a debris basin with a maintenance access ramp and an overflow standpipe, resulting in the City having permanent rights to a facility that will function to protect Foothill Boulevard from storm flows overtopping the roadway. A Project Study Report is to be prepared to determine the Scope of Work and the required right of way.
Soundwall Phase IV The project includes 3 remaining wall segments to reduce exposure to traffic noise from Walton Dr. to Glenhaven Dr., La Grenada Blvd. to Angeles Crest Hwy., and Commonwealth Ave. to Oakwood Ave. Process Cooperative Agreement with Caltrans and preparation of RFP for design service.
Soundwall Phase V Future soundwall projects will address the 14 remaining eligible wall segments to be constructed throughout the City. TBD