Projects Out to Bid
Title | Bid Opening | Bid Results |
---|---|---|
2021 CITYWIDE RESURFACING PROGRAM
GET A COPY OF THE BID PACKET BY FILLING OUT THE FORM BELOW:
|
2:00 p.m. on Thursday, January 7, 2021 | Bid Results |
Requests for Proposals
Title | Due Date |
---|---|
Sister Cities Friendship Trail (Alternate Entrace for Descanso Trail)
GET A COPY OF THE RFP BY FILLING OUT THE FORM BELOW:
|
Prior to 4:00 P.M., December 17, 2020 |
Capital Improvement Projects (CIPs) are considered a major, non-routine expenditure for new construction, major equipment purchases or improvements to an existing building, facility, land, streets, storm drains, or utilities, or the expansion of the City parks system.
Active Project Status
UNDER CONSTRUCTION
Title | Description | Status |
---|---|---|
2020 Citywide Street Resurfacing | The project includes resurfacing of 23 street segments throughout the City, with an approximate distance of 4.5 miles. | Construction started on June 1, 2020 and pavement of all streets was completed on July 31, 2020. The remaining work consists of painting of house numbers and supply and installation of standard and illuminated street name signs. The remaining work is now expected to be completed by October 15, 2020.
ESTIMATED COMPLETION DATE OF October 2020 |
Miscellaneous Concrete Repair | The City maintains and repairs miles of curbs, gutters, and access ramps, as they are damaged by traffic or by tree roots or have simply deteriorated due to age or use. | On May 5, 2020, the City Council awarded the Contract to the lowest bidder CT&T Concrete Paving, Inc., in the amount of $109,200. Construction started on July 20, 2020 and to be completed by September 15, 2020.
ESTIMATED COMPLETION DATE OF SEPTEMBER 2020 |
Foothill Bouelvard Street Restripping | The project includes restriping Foothill Boulevard from Alta Canyada Road east to Oak Grove Drive and striping median noses from Briggs Avenue to Oak Grove. | On June 16, 2020, the City Council awarded the Contract to the lowest bidder, PCI, in the amount of $136,034. Construction started on August 17, 2020 and to be completed by September 17, 2020.
ESTIMATED COMPLETION DATE OF SEPTEMBER 2020 |
IN DESIGN PHASE
Title | Description | Status |
---|---|---|
Seco Creek Trail | The project involves environment analysis of the user made trail and construction to ensure the trail complies with current trail standards. | Design= Completed Environmental Permits= In Progress and to be completed by end of September 2020, after which the project will be advertised for construction bids in October 2020 and to be awarded in November 2020.
ESTIMATED START CONSTRUCTION DATE FALL 2020 |
Soundwall Phase II | The project includes 1 wall segment to reduce exposure to traffic noise on the south side of the 210 Freeway from La Toure Way to Alta Canyada Road. | Design = In Progress, to be completed in Spring 2021 Environmental = In Progress, to be completed in Spring 2021 ROW = In progress, to be completed in Spring 2021 Receive Caltrans’ Approval to advertise for construction in summer 2021, after which the project will be advertised for construction bids.ESTIMATED START CONSTRUCTION DATE FALL 2020 |
Soundwall Phase III | The project includes 3 wall segments to reduce exposure to traffic noise; one wall on the north side of the I-210 Freewayand one wall on the south side of the Foothill Boulevard highway overpass; and 3rd wall on the south side of I-210 Freeway from Alta Canyada Road to the bridge over the freeway at Memorial Park. | Design = In Progress, to be completed in Spring 2021 Environmental = In Progress, to be completed in Spring 2021 ROW = In progress, to be completed in Spring 2021 Receive Caltrans’ Approval to advertise for construction in summer 2021, after which the project will be advertised for construction bids.ESTIMATED START CONSTRUCTION DATE FALL 2020 |
Foothill Boulevard Traffic Signal Improvements | The project includes safety improvements to existing traffic signals at 4 intersections with Foothill Boulevard to enhance safety at each intersection, reduce the potential for traffic collisions, and improve traffic flow. | Design = In Progress – Consultant submitted 35% plans and estimate on August 24, 2020 for City review.
ESTIMATED START CONSTRUCTION DATE SPRIN 2021 |
Descanso Drive Street Improvement | Descanso Drive, from Chevy Chase Drive to Verdugo Boulevard, rehabilitation of pavment and other related improvements. | Design = In Progress; it is expected to be completed by end of December 2020, after which the project will be advertised for construction bids in January 2021.
ESTIMATED START CONSTRUCTION DATE SPRING 2021 |
2021 Citywide Resurfacing | Resufacing of approximately 2.5 miles of various segments of roads in the City. | Design = In Progress, it is expected to be completed by end of December 2020, after which the project will be advertised for construction bids in January 2021.
ESTIMATED START CONSTRUCTION DATE SPRING 2021 |
FUTURE PROJECTS
Title | Description | Status |
---|---|---|
Soundwall Phase V | Future soundwall projects will address the 14 remaining eligible wall segments to be constructed throughout the City. | TBD |